Waste storage points: checking the three-tonne limit

Distinguish storage points from facilities and check stock, records and collection arrangements.

Content publication record:

Published on 20 November 2026.

Does every hazardous waste storage area in Shanghai have a three-tonne limit?

No. The three-tonne limit must not be applied indiscriminately to every hazardous waste storage area. Clause 8.3.5 of GB 18597-2023 applies to hazardous waste storage points. The Ministry of Ecology and Environment explains that this is the total hazardous waste held at a storage point at any instant. It is not three tonnes for each waste type, nor three tonnes generated over a year.

First distinguish a storage point from a storage facility. Under clause 3.8, storage points include dedicated storage areas at the same production or business premises of waste generators subject to registration management, and areas near production lines used by waste generators for temporary transfer. Clause 3.3 lists storage warehouses, storage yards, storage pools and tank farms as storage facilities. Calling an area a 'hazardous waste room' does not determine its category. This distinction does not allow unlimited storage at a facility: its capacity and management arrangements still need to be assessed against waste characteristics, quantities, environmental risks and applicable requirements.

Before arranging hazardous waste treatment, a Shanghai enterprise can gather the location and use of the storage area, waste categories, stock quantities at relevant times, and incoming and outgoing records. These help clarify the type of area and collection arrangements. This is a suggested preparation list, not a universal official application checklist. Do not substitute annual waste generation for the quantity held on site. Holding less than three tonnes does not remove applicable packaging, seepage-prevention or leak-prevention requirements.

This answer supports a review of routine storage arrangements. It does not establish whether a particular facility is compliant or replace the response required for a leak or other incident. Shanghai Conghe Environmental Protection Technology Service Center (Conghe Environmental Protection) can help organize records and documents and coordinate disposal arrangements. Actual receipt, transport and treatment must be undertaken by operators meeting the applicable requirements.

MEE explanation (Chinese) · GB 18597-2023 (Chinese)

Unofficial English explanation; the official Chinese standard and guidance govern.

Official Sources

These sources explain requirements; they do not imply endorsement of this company. Confirm current applicable requirements before proceeding.

  1. Ecological and Environmental Code: Articles 532–537 and 1242 (Chinese)
  2. MEE: Technical Guideline for Hazardous Waste Management Plans and Ledgers, HJ 1259–2022 (Chinese)
  3. MEE: official explanation of HJ 1259–2022 (Chinese)
  4. Shanghai Municipal Bureau of Ecology and Environment: hazardous waste operating licence list (Chinese)

Service Enquiries

For front-end document or process support, contact Shanghai Conghe Environmental Protection Technology Service Center. For actual receipt or treatment, identify the operator and applicable authorisation separately.

Phone:15317893386 / 13601827217 WeChat:17091907360